Site is located at Shebily area - Khobar city.

  • Excavation depth was about 9.00m ( Two basement )

  • Excavation works amount 24,000 m3

  • Soldier pile shoring system was used

  • Anchoring work for one row to support shoring system

  • About 90 anchors were used total length = 15.00 m

    fixed length = 10.00 m free length = 5.00 m four strands size 15.70

  • Dewatering system using well point system for two levels using about

    8 dewatering pumps.

  • Concrete work of 2.00 m thickness raft ( 4,500 m3)

  • Retaining walls of the two basements

  • 23 slabs upper ground level

Al-Sahly Tower

( Shebily – Khobar )